Orica is conducting a remediation project at a site in Yarraville, Melbourne.

This webpage provides information on the project, access to key documents and a project schedule that will be updated as planning and the project progresses.

Project Overview

The remediation project will address nitrogenated hydrocarbon and chlorinated hydrocarbon (CHC) contamination, associated with past manufacturing operations. It will include two distinct activities: 

  1. Excavation of contaminated soil for transport and thermal treatment at a licensed off-site facility; and 
  2. Remediation of soil and shallow groundwater, involving a technology called “in-situ thermal desorption” (ISTD), where gas fired thermal heaters are drilled into the ground to a depth of up to 8m. The soil is heated to approximately 100°C and the volatile hydrocarbons are extracted and treated in a small on-site treatment plant.

The area proposed for remediation via excavation and one of two ISTD remediation areas have been completed. The final ISTD remediation area is planned to be conducted and completed by the end of 2022. 

The project is being conducted in accordance with Environment Protection Authority Victoria (EPA) requirements under a Clean Up Notice issued in June 2020. 

More information is included in the Fact Sheet below. 

Key Documents

Project Timing

The current project schedule is shown below. This is subject to change and will be updated as the project progresses. 

 

Activity 

Current Timing 

 Pilot trial excavation / treatment  Complete [2018]
 EPA project review   Complete [2018]
 Site establishment  Complete [January 2019]
 Demolition, Excavation & Off-site Thermal treatment   Complete [February - October 2019]
 In Situ Thermal Description (ISTD) Area 1  
 ISTD preparation works  Complete [June - October 2019]
 Construction  Complete [October - November 2020]*
 Commissioning  Complete [December 2020]*
 Operation  Complete [December 2020 - June 2021]*
 In Situ Thermal Description (ISTD) Area 2  
 Construction  November 2021 - May 2022
 Commissioning  May 2021
 Operation  May - November 2022
 Demobilisation  November - December 2022
 Final site re-grading   January - March 2023

* ISTD remediation works are being completed by a specialist contractor from the USA and works were impacted by travel restrictions that were implemented by the Australaian Government, to protect the health of the Australian community from the spread of COVID-19. Works were put on hold between April and October 2020 until exemption to the travel restrictions were granted.

Stakeholder Consultation

Orica has engaged with its neighbours, the nearby community and other stakeholders regarding the Yarraville Remediation project through meetings, face to face discussions, letters, emails and phone calls.

Consultation will be maintained with interested parties throughout the project to ensure questions can be addressed and feedback responded to in a timely manner. 

Contact Us

If you would like further information about this project, please contact us at: 

General Enquiries

Email: [email protected] 
Tel: +61 3 9665 7642

Street Address

325 Whitehall Street
Yarraville VIC 3013